Kincardine piers to remain closed until repairs are done

Liz DadsonBy: Liz Dadson  April 27, 2021
Kincardine piers to remain closed until repairs are done
The north and south piers at Kincardine Harbour remain closed because they are unsafe and require extensive repairs.

That’s the word from recreation director Karen Kieffer who presented a report about beach safety to Kincardine council, in committee-of-the-whole, Monday night (April 26).

Kieffer said staff reviewed the proposed recommendations presented to council by a delegation March 1, and there are some that can be implemented immediately, others that can wait until next year, and some that cannot be implemented.

Under Phase 1 (2021), Kieffer included the following:

Communication enhancements – Staff has $5,000 for new signage in the 2021 parks operating budget. The plan is to install new educational signs with QR codes that will highlight rip currents, designated swimming, no swimming areas, etc. The recommendation for a second Automated External Defibrillator (AED) at the fish cleaning station was considered not useful because there is one at the Kincardine Marina office – improved signage will be installed showing the location of the AED.

No parking area – The area between the boardwalk and boat launch, below the south pier, will be designated a no-parking zone and no-parking signs will be installed. This area would also be included in the parking bylaw.

Pier railing – Before consideration can be given to installing railings along the piers, staff believes that repairs must be completed first.

Kieffer said municipal engineer B.M. Ross and Associates did a structural review of both piers and the cost to fix them is about $210,000.

The south pier is in poor shape and is “no longer structurally reliable to support normal pedestrian loads because of the deterioration of the support framing,” said Kieffer. It should remain closed until repairs are completed.

The recommendation is to fill the voids with a low-pressure grout, and to patch-repair the deck surface and restore some of the safety ladders. The preliminary budget for this work is $160,000.



The north pier (above) is in better condition, structurally, and is deemed safer for normal pedestrian traffic, said Kieffer. However, the concrete spalls should be repaired along with the safety ladders within the next five years at a current estimated cost of $50,000. There are also some areas of deck deterioration that should be repaired to restore the original strength and to reduce trip hazards.

Kieffer recommended the work be done this year and the $210,000 come from the municipality’s contingency reserve fund.

Under Phase 2 (2022), are the following:

Rescue board – Staff will investigate who exactly would be trained to use it if one were required for a water rescue, and what the training for this would look like. Staff will also consult municipal emergency personnel and rescue teams to inquire if there are any risks or concerns with using and/or having this board available for the public to use in rough waters.

Beach warning light - As this is new technology for the municipality, staff will need to work with Nuclear Promise X (NPX) as it completes its prototype, and possibly allow for a period of testing to ensure that the light is accurately communicating current conditions. Staff will also need to investigate how this warning light would work operationally in terms of daily inspections required to ensure equipment is functioning properly, how power outages might affect the equipment, any liability issues the municipality may face, etc.

EMILY remote-operated rescue device - Staff needs to investigate the feasibility of this rescue device in rough waters and have discussions with existing rescue agencies to determine usability of this rescue device, as well as who exactly would be responsible for the operation of it, training required, etc.



Station Beach, Kincardine

Kieffer said staff is not recommending Kincardine implement a beach patrol.

“We did seek a legal opinion and were advised that the staffing of lifeguards on the beach could open up the municipality to liability,” she said. “Where there is no lifeguard present, the duty of care is to provide signs or other safety devices, as necessary, to keep a beach reasonably safe. There are very specific waterfront safety standards and qualifications required for lifeguarding at a waterfront versus lifeguarding at a pool. Currently, we do not have any existing staff members who are waterfront certified.

“Factors to consider would be costs associated with this certification, having sufficient staff to lifeguard both the waterfront and the pool at the same time, the frequency of how often the beach would need to be lifeguarded and when, what sections of the beach would be guarded, expectations in adverse weather conditions, having to close the beach if no lifeguards available, etc. These are all factors that would require significant consultation and consideration if this option were to be explored further.

“Finally, from a staff perspective, there are significant concerns about the safety and well-being of our employees and the possibility of putting their lives in danger while on duty guarding a waterfront.

Kieffer said other beach initiatives include:
 
  • Developing beach signage that would include an indicator of where a person or situation is requiring assistance on the beach; for example, if calling 911
  • Updating education messaging on municipal websites and social media platforms
  • Reviewing and updating safety equipment at municipal beaches, including Inverhuron Beach, Sunset Beach, etc.

“The piers are in dire need of repair,” said councillor Doug Kennedy, policy chairman for parks and recreation. “We know it costs money, but it’s important, in order to keep people safe.”

Councillor Dorne Fitzsimmons asked if the south pier was currently closed, because social media showed surfers using it on the weekend.

“Both piers are closed to the public,” said Kieffer. “If council approves moving forward with these repairs, we will find a better way to keep people off them.”

She added that in order to expedite the process, B.M. Ross would like to approach three companies that do this kind of work, rather than put the project out to tender.

“I’m asking for council’s consideration to use a request-for-quotations process in order to get quotes and bring them back to council,” she said. “That would be quicker than the tender process.”

Committee-of-the-whole agreed with that, as well as the recommendation to move ahead with the beach safety enhancements for 2021, keep the piers closed until the repairs are done, and complete the repairs this year, with $210,000 from the contingency reserve fund.

That was later endorsed by council.
 
In addition, Kieffer told the Kincardine Record that the marina boat launch is open, but only for anglers, not recreational boating. Also, the Kincardine Yacht Club has postponed the annual boat lift-in, which is usually held in May.

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad