Huron-Kinloss defers proposed Ripley Outdoor Plaza, for now
Huron-Kinloss council has deferred the idea of a proposed Ripley Outdoor Plaza, for now.
At the committee-of-the-whole meeting May 3, the project came forward for debate, with a plaza and parking lot slated for the corner of Huron and Jessie Streets in Ripley, beside the Ripley-Huron Fire Hall.
Three years ago, the township had a conceptual drawing prepared to include nine parking spaces and a large plaza area with benches, trees, greenery and space for markets, events, etc. This was a part of a much-bigger economic development project to increase investment in Ripley, to create a downtown that the residents could enjoy, to recruit and retain businesses that residents and visitors could support, but most importantly, to ensure the village could remain a vibrant, spirited community for decades to come.
The conceptual drawing was circulated throughout the community, presented to the Ripley-Huron Fire Department, and public input was invited. When the first design was presented, the feedback was that there was an overwhelming need for more parking in the downtown core.
So, two alternate designs were created by B.M. Ross and Associates:
- Plan A: 35 standard-size parking spaces and two accessible parking spaces
- Plan B: 25 standard-size parking spaces, two accessible parking spaces, and a modest-sized outdoor plaza
The report presented to council May 3, came from community development officer Michelle Goetz, with support from chief administrative officer Mary Rose Walden, clerk Emily Dance, public works director John Yungblut, fire chief Chris Cleave, and community services director Mike Fair.
It states that in 2019, students from Fanshawe College produced some design options, and those were posted on-line for public input.
The majority of the votes were in favour of Plan A (35 parking spaces), with 132 votes, compared to Plan B (25 parking spaces and the plaza), with 78 votes.
Many of the concerns were due to the project’s proximity to the fire hall – delayed response times for the firefighters, lack of parking for firefighters, dangerous situation when the firefighters are responding to calls, and limiting future expansion of the fire hall
Cleave said he supports any draft design that allows for both a plaza and designated parking for the firefighters that is segregated and not accessible to the plaza, or with some type of clear barrier in place dividing the two. He said construction of an outdoor plaza at this location would not have any impact on the firefighters’ response times so long as any parking that is assigned to the fire department is clearly marked and protected from the outdoor plaza area.
The public commented that funding should go toward improving Lewis Park and creating space for markets/events, rather than putting up an outdoor plaza just a block away. Or using the Bruce Botanical Food Gardens location.
People commented that more downtown parking is needed, and that a paved parking lot would be easier for the township to maintain. There were suggestions to consider municipal parking lots away from the fire hall, such as the lot between Lewis Park and the Hensall Co-op or behind the curling club in the well-head protection zone.
The township is planning to apply line painting for the parallel parking spaces on Huron Street, from Tain Street to Queen Street, this year, and expects that improved parking organization will increase the access to parking in the downtown core. If council decides to move forward with public parking, it is recommended that there be no overnight parking permitted and a two-hour limit.
There were additional public comments suggesting planters and park benches to beautify the space if it were used for parking only. A response received encouraged the municipality to integrate more green spaces into the community to aid in the fight against climate change.
The public is concerned about turning this prime commercial lot into parking and a plaza. The respondents questioned whether this was the right spot for a municipal parking lot; parking is required but municipal parking lots are usually built off the main downtown core to ensure prime commercial areas are available for investment.
Others questioned what other beautification/economic development projects the township should be prioritizing before a plaza or parking. One respondent suggested approaching the owner of the vacant lot beside FIG Studio Kitchen, to create a temporary gathering space/plaza to encourage investment in that prime commercial lot.
The vacant lot at the corner of Huron and Jessie Streets, beside the Ripley-Huron Fire Hall, is being considered for an outdoor plaza and parking; photo courtesy of Huron-Kinloss Township
Staff reviewed the comments and mitigation measures, and recommended moving forward with a type of beautification design in downtown Ripley that provides a segregated parking area for firefighters when responding to calls.
In addition, letters were sent out to request feedback regarding the rehabilitation of the interlocking bricks at the four-way stop at Huron and Queen Streets in Ripley, and the interlocking-brick crosswalks.
There was no feedback from these letters. So, the recommendation was to pave the four-way stop and the crosswalk in order to save considerable funds in construction and maintenance, and to ensure accessibility at these locations. Funds from this project can be used toward the parking area of the vacant lot at Jessie and Huron Streets.
The current estimate for a proposed plaza and parking lot is $190,000. The 2021 capital budget includes $290,000 for the replacement of the interlocking bricks with concrete pavement; however, the current estimate for converting the bricks to asphalt is $120,000.
Staff’s expectation is that by combining the Ripley Outdoor Plaza, the Ripley main intersection, Melville Lane reconstruction and the construction of sidewalks on Queen Street and William Street North, into one tender, the township would take advantage of economies of scale and the totality of the projects would be within budget. There is sufficient funds from the Ripley Beautification Reserve to pay for the concrete plaza and landscaping.
During discussion, council decided to leave the vacant lot as a gravel parking lot, for now, and deferred the proposed outdoor plaza project. The work at the main intersection in Ripley will proceed.
Written ByLiz Dadson is the founder and editor of the Kincardine Record and has been in the news business since 1986.
Related Stories
No related stories.