Bruce Power removes first steam generator in Unit 6 MCR
Bruce Power’s Unit 6 Major Component Replacement (MCR) project reached a much-anticipated milestone, July 23, with the successful removal of the first steam generator from the station.
“The steam generator replacement is a major milestone for the Unit 6 MCR, and represents years of hard work and collaboration between Bruce Power and such partners as SGRT, BWXT, Mammoet, Nuvia, and the Building Trades Unions," said Mike Rencheck, Bruce Power’s president and chief executive officer.
“Bruce Power’s ‘Made-in-Ontario’ nuclear supply chain supports Canada’s largest private infrastructure and clean energy project, which injects billions into Ontario’s economy and creates and sustains 22,000 high-skilled jobs annually.”
Unit 6 contains eight steam generators which are arranged vertically in two columns of four on the east and west side of the reactor. Each steam generator weighs approximately 320,000 pounds and will be lifted through the powerhouse roof enclosure using Mammoet’s PTC-35 crane. This 1,600-ton capacity crane is one of the largest in the world and features a boom the length of a hockey rink that can stretch over the (seven storeys tall) station and reach the inner-most steam generators.
The first steam generator is removed from Unit 6 at the Bruce Power nuclear generating station, west of Tiverton; photos courtesy of Bruce Power
The new steam generators were fabricated at BWXT in Cambridge and shipped to site in late 2020. Laser topography was conducted on the steam generators to transform them into a 3D layout to verify dimensions prior to the first lift. These will be set in place by building trades within a few millimetres tolerance.
The Steam Generator Replacement Team (SGRT), a 50-50 joint venture between Aecon and SGT (a partnership between Framatome and United Engineers and Constructors), is Bruce Power’s vendor responsible for removing the Unit 6 steam generators, and was recently awarded a contract to replace the steam generators at Units 3 and 4.
“This first lift was preceded by half a decade of preparations and was completed successfully thanks to our safe work plan and highly-skilled construction trades, as well as strong collaboration and communication with our vendor partner, SGRT,” said Eric Chassard, executive vice-president of projects and engineering at Bruce Power.
“The team is now focused on the safe execution of the 15 remaining lifts, which will be finished next month. We’re looking forward to marking off another successful milestone for the MCR project.”
The first steam generator is removed from Unit 6 at the Bruce Power nuclear generating station, west of Tiverton