EPCOR Southern Bruce Gas Inc. is hosing public information sessions in Kincardine, Ripley and Chesley, about the proposed natural gas project.
Last month, the company, which is based in Edmonton, Alberta, received word from the Ontario Energy Board (OEB) that it had been selected to provide natural gas to the three Southern Bruce municipalities.
EPCOR has retained Stantec Consulting Ltd. to do an Environmental Study of the proposed distribution network and natural gas transmission pipelines.
The pipeline system will be about 300 kilometres long, with 168 kilometres of natural gas distribution network. It will run from the Dornoch Station in Chatsworth Township, to Lucknow in Huron-Kinloss Township.
The project will service the Bruce Energy Centre, Kincardine, Inverhuron, Tiverton, Chesley, Paisley, Ripley, Lurgan Beach, Point Clark and Lucknow, as well as residences, and commercial and industrial businesses along the route.
The information sessions will be held
Wednesday May 23, from 5- 8 p.m., in the main hall at the Davidson Centre, Kincardine; Thursday, May 24, from 5-8 p.m., at the Chesley Community Centre; and Friday, May 25, from 5-8 p.m., at the Ripley-Huron Community Centre auditorium.

Robert Croghan (left) co-gen consultant with EPCOR, and Thomas Stachowski, EPCOR customer care representative for EPCOR, hold up a map showing the natural gas pipeline route, at the press conference in Kincardine, April 17
Shortly after hearing it had been chosen for this project, EPCOR held a press conference in Kincardine where vice-president of business development Karim Kassam explained that the company is here for the long-term.
“Three years ago, we jumped on the bus to bring natural gas to Southern Bruce,” he said. “Now, we're going to stay on for the full ride.”
He said EPCOR's project, as submitted to the OEB, will cost about $60-million to $80-million, which is significantly reduced from the $100-million quoted seven years ago by Union Gas. The cost could be even lower, he said, depending on what Union Gas charges for the connection to the Dornoch Station.
Kassam said the hope is for EPCOR to submit its Leave to Construct to the OEB by October, with construction beginning next spring. The first section would be connected by late fall 2019, most of the area hooked up by 2020, and the entire three municipalities connected by 2021.
“This is an exciting time for us at EPCOR,” he said. “We want to start building the pipeline as soon as possible.”
Gathered for a press conference regarding the Southern Bruce natural gas project, are EPCOR's Thomas Stachowski (left), Gord Kaiser, and Karim Kassam; Arran-Elderslie mayor Paul Eagleson and Huron-Kinloss mayor Mitch Twolan
During a question-and-answer portion, Kassam said the project will begin with a connection to the Bruce Energy Centre, then into Kincardine, Chesley and Paisley, followed by the southern communities of Point Clark, Ripley and Lucknow.
He said that once the original project is completed, EPCOR would consider expanding the pipeline into other nearby neighbourhoods, industries and businesses.
In answer to a question about jobs, Kassam said that during the construction phase, the project could generate up to 200 jobs. Once construction is completed, there would be 10 full-time jobs required for operations.
As for the proposed rates for natural gas, Kassam said EPCOR will have to discuss the cost with larger consumers before setting the residential rates.
He said there is a municipal incentive. All three municipalities have given the company a tax exemption for 10 years for the pipeline project, which amounts to just under $1-million per year.
Regarding concerns that the $23.7-million in provincial funding for the project would disappear after the Ontario election June 7, Kassam said that funding has been committed by the province and will be there after the election.
Gord Kaiser, former vice-chairman of the OEB and a regulatory consultant with EPCOR, echoed those sentiments. “The government funding cannot be pulled because this project has gone through a regulatory process.”
For more information about the natural gas project, check the website at:
www.epcorsouthernbruce.com.
Standing with the map of the natural gas pipeline route, are EPCOR's Robert Croghan (left), co-gen consultant; Thomas Stachowski, customer care representative; Karim Kassam, vice-president of business development; and Gord Kaiser, regulatory consultant; Kincardine mayor Anne Eadie, Huron-Kinloss mayor Mitch Twolan, and Arran-Elderslie Paul Eagleson
Written ByLiz Dadson is the founder and editor of the Kincardine Record and has been in the news business since 1986.
Related Stories
No related stories.