Debate at budget meeting ends in 6-2 vote for servicing Kincardine Business Park
Kincardine's second budget meeting saw a lengthy debate about the initial phase of servicing for the Kincardine Business Park, southeast of Highways 9 and 21.
In committee-of-the-whole Monday, Jan. 14, treasurer Roxana Baumann explained that this project is included in the 2019 capital budget at a cost of $4.265-million. Funding would come from, in part, the hosting payment for the proposed Ontario Power Generation (OPG) Deep Geologic Repository (DGR) for low- and intermediate-level nuclear waste at the Bruce site (about $450,000) plus external borrowing of $3.815-million.
With a loan term of 10 years, and at an interest rate of 3.4-per-cent, annual loan payments would amount to about $454,000, said Baumann, adding that the servicing costs would ultimately be funded by development charges, similar to the Ontario Peninsula Farms lands, north of the Sutton Park Mall.
Baumann recommended that council allocate the annual OPG DGR payments toward the annual loan repayments for this project. The hosting agreement payments are to continue at the 50-per-cent level until either OPG decides to terminate the DGR project, or the government allows it to proceed.
Councillor Bill Stewart said he still cannot support the servicing of the business park, and does not want to invest all the OPG money into it. “If you're going to do that, you should just go ahead and borrow the whole amount,” he said.
Councillor Gerry Glover said he appreciates that raising taxes is not ideal and is a stumbling block for new councillors, “but development and growth are happening everywhere but Kincardine. We need to move forward on this even though it's not popular. People are asking why there's not more infrastructure here. We need economic development to thrive.”
“I ran my campaign on economic development,” said deputy mayor Marie Wilson. “Throughout the election campaign, the comments I heard were why don't we have this or that business, why are we lagging behind other communities? We have a specific window of opportunity, with so much going on – the Bruce Power MCR (Major Component Replacement) project, 7ACRES expanding. There is a buzz out there. There's a lot going on, and I believe the time is right to do it now. It's an investment and we will recoup the cost through area specific development charges.”
“I'm not against development,” argued Stewart. “I just think it's too much of a risk. We have 68 acres of land at the Ontario Peninsula Farms location, and I'm concerned that all we have is the Bruce Power training facility there. If we get the services in place and nobody builds, then we have a problem. The property (at Highways 9 and 21) is owned by Smart Centres.”
“Not all the land,” said mayor Anne Eadie.
“I don't support it; there's too much risk,” said Stewart.
“There's too much risk if we don't go ahead,” replied Eadie.
Chief administrative officer Sharon Chambers said the land north of the MCR training facility is not envisioned as a business park. “The property at Highways 9 and 21 was the municipality's focus. There have been multiple land owners developing at different rates. We do hear from developers all the time. In fact, a lot sold recently and the owners are just waiting for servicing. Another developer has plans and is ready to go. They don't want to wait two to three years for servicing.”
Eadie said proper servicing has been extended into the land north of the Sutton Park Mall which would be ideal for residential development.
Public works director Adam Weishar said the the water and sewer services were extended from Russell Street across Highway 21 last year. This year, the work would include water, sanitary sewer and storm sewer work, as well as a road system, on Russell as far as Millennium Way, across to the edge of Sobeys and then east along the south end of the Marriott Hotel.
Weishar said no more property can hook into Durham Street because its pumping station is at capacity.
In a recorded vote, Eadie, Wilson, Glover and councillors Maureen Couture, Dave Cuyler and Doug Kennedy voted in favour of the project, while Stewart and councillor Randy Roppel voted against. It was approved, 6-2. Councillor Laura Haight was absent.
Council discussed other high-priced capital projects, including:
- A generator for the municipal administrative centre ($300,000), turned down until it is determined the centre will be used as the municipality's emergency operations centre
- Road reconstruction ($755,000), on Concession 5 from Bruce County Road 23 to the west end, storm sewer and paving, approved
- Rural paving ($350,000), Kincardine-Kinloss boundary – shared 50-per-cent with Huron-Kinloss
- Rural paving ($925,000), various concession roads at $155,000 per kilometre, approved
- Plow truck ($325,000), approved
- New loader ($255,000), approved
- Replace PLC and new fire pump in Tiverton Water Tower ($500,000), approved
- Replace existing fire pump in Kincardine Water Tower ($500,000), approved
- Demolish grandstand at Connaught Park due to safety concerns ($30,000), approved
- Bervie Park, new playground replacement and surfacing ($40,000), approved
At the council meeting Jan. 9, the following capital projects received pre-budget approval:
- Student job in cemetery department, $6,850
- Recreation program registration software, $60,000
- Roof projects at Kincardine Airport, Tiverton Library and Kincardine Arts Centre, $407,000
- Lighthouse restoration, final phase, $375,000
- Agenda management software, $15,000
- Community engagement software, $8,000
Eadie said council still needs to discuss what to do with the Whitney Crawford Community Centre in Tiverton, and Phase 3 renovations at the Kincardine Arts Centre.
That wrapped up the budget meeting, with the next meeting slated for Wednesday, Jan. 30, at 5 p.m., in the municipal administrative centre.
Currently, the draft budget includes a 3.8-per-cent municipal tax rate increase which equates to an additional $67 on the average residential assessment of $270,000. Once the Bruce County levy and educational tax are added, the overall tax increase is 2.05 per cent.
Written ByLiz Dadson is the founder and editor of the Kincardine Record and has been in the news business since 1986.