Opening of Queen Street bridge, Kincardine, delayed to mid-October
Due to unforeseen delays, the opening of the Queen Street bridge in Kincardine has been postponed to mid-October.
Public works director Adam Weishar, says the delay is due, in part, to the COVID-19 (Coronavirus) pandemic, as well as other factors.
“We incurred a week's delay due to existing telecom infrastructure that was not known,” he says. “The opening was to occur this past Friday (Sept. 18) but there are works that remain.
“To allow the contractor to perform those works safely and to ensure they are done as efficiently as possible, the bridge will remain closed a few additional weeks.”
The structure has been closed since April 1. The work included removal and replacement of the concrete parapet wall and sidewalks, deck-top repairs, beam repairs, and replacement of the leaking expansion joints, followed by waterproofing and paving the bridge deck.
The project also included replacement of the watermain hanging from the bridge, and on the approaches to the bridge, new curb and gutter, new sidewalk, new stormwater structures, and installation of new light poles.
The Queen Street bridge in Kincardine is slated to re-open in mid-October

The Queen Street bridge, looking south from Victoria Park